Title Report Date Time Cost Scope Overall Change
Report for May 2022 May 2022 BLUE BLUE BLUE BLUE
Report for April 2022 April 2022 RED RED RED RED No Change
Report for March 2022 March 2022 AMBER GREEN GREEN AMBER No Change

Project Info

Project
API Upgrade
Code
COM068
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Bill Lee
Current Stage
Plan
Status
Withdrawn
Start Date
14-Mar-2022
Planning Date
08-Apr-2022
Delivery Date
15-Jul-2022
Close Date
29-Jul-2022
Overall Priority
Normal