Report for April 2022
- Report Date
- April 2022
Achievements this period
- No progress due to resourcing issue
Issues
- Additional resources being provided to People and Money - (COR005) has meant that the capacity in Development Services has been greatly reduced. The resource request from People and Money has a very high priority, therefore a number of projects are seeing either a reduction in the resource availability, or the resource being unavailable. COM068 will not get resource to continue, therefore it is very likely the project will be withdrawn.
Next Steps
- Decision on whether the brief should be written up, then suspended, of if the project should be withdrawn from this financial year
Milestones
N/A
- Approved budget
- 65.0 days
- Activity this month
- 1.5 days
- Activity this year
- 4.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 58.0 days
- Estimate to complete future years
- 0.0 days