November Report
- Report Date
- November 2013
Achievements in last period
- Initial discussions with Reporting and Analytics team regarding potential BOXI requirements
- User Stories Prioritisation meeting held on 06/11
- Environment provisioning for Dev, BETA, Test and Live
- Foundations Milestone completed 22nd Nov
- Review of design mock-ups completed with Product Owners
- Development iteration 1 completed on 29th Nov with review undertaken to assess 2 user stores completed
- Prioritisation of user stories for Development Iteration 2
Issues
- Development Iteration 1 delayed by 1 week due to environment builds not completed on time due to delays in ITI UNIX provisioning of functional accounts
- Following discussions with Product Owners the budget has been increased by 45 days to allow a further 3 development iterations to be made available to provide a more robust compliant system for users. This has been submitted to WIS for approval.
Next Steps
- Development Iteration 2 review
- Prioritisation of user stories for Development Iteration 3
- Development Iteration 3 review
- Approved budget
- 165.0 days
- Activity this month
- 21.6 days
- Activity this year
- 38.2 days
- Activity to date
- 38.2 days
- Estimate to complete current year
- 132.8 days
- Estimate to complete future years
- 0.0 days