December report

Report Date
December 2013

Achievements in last period

  • Development iteration 2 and 3 completed.
  • Prioritisation of user stories for Development Iteration 4.
  • Additional milestones added for development iteration 7-9

 

Issues

  • BETA environment issues resolved and available for use, BETA and DEv environments impacted due to 503 errors which are being investigated by Development Technology.
  • Development Iteration 3 impacted by Development AppDev Migration under project  ITS103 therefore not all development code could be promoted from Dev to Beta during iteration timescales.
  • Development resource days reduced on Development iteration 3,  due to support of Live issues encountered on SAGE application project.

 

Next Steps

  • Development Iteration 4
  • Prioritisation / re-estimation of remaining user stories for later Development Iterations
  • Development Iteration 5, 6, 7 review
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
165.0 days
Activity this month
24.3 days
Activity this year
60.2 days
Activity to date
60.2 days
Estimate to complete current year
109.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Accident & Incident Reporting
Code
CSG002
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Karen Stirling
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
10-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Jun-2014
Overall Priority
Normal
Category
Compliance

Documentation