December report
- Report Date
- December 2013
Achievements in last period
- Development iteration 2 and 3 completed.
- Prioritisation of user stories for Development Iteration 4.
- Additional milestones added for development iteration 7-9
Issues
- BETA environment issues resolved and available for use, BETA and DEv environments impacted due to 503 errors which are being investigated by Development Technology.
- Development Iteration 3 impacted by Development AppDev Migration under project ITS103 therefore not all development code could be promoted from Dev to Beta during iteration timescales.
- Development resource days reduced on Development iteration 3, due to support of Live issues encountered on SAGE application project.
Next Steps
- Development Iteration 4
- Prioritisation / re-estimation of remaining user stories for later Development Iterations
- Development Iteration 5, 6, 7 review
- Approved budget
- 165.0 days
- Activity this month
- 24.3 days
- Activity this year
- 60.2 days
- Activity to date
- 60.2 days
- Estimate to complete current year
- 109.3 days
- Estimate to complete future years
- 0.0 days