April Report
- Report Date
- April 2014
Achievements in last period
- Product Owners carrying out their post implementation activities
- Project closure report issued to Product Owners for comments waiting updates to be provided
- Bug fixes / change completed and tested waiting for Apps Managemnet resource to deploy to live
- Revise closure milestone expected now 30/05/2014
Issues
- Further change requested by Product Owners to amend date order of incidents displayed
- Product Owners limited availability to review Business Objects Info Space area within Service Management now completed until 3rd week April
- Beta Server impacted by network SAN issues between 22/24 April delayed promotion of code to BETA and TEST environments
Next Steps
- Promote code fix to live scheduled for 12th May
- Business Objects activity to be promoted to live waiting for confirmation of Apps Management resource
- Closure submit to WIS for approval
Project AMBER as waiting for confirmation of resource
- Approved budget
- 184.0 days
- Activity this month
- 0.7 days
- Activity this year
- 183.3 days
- Activity to date
- 183.3 days
- Estimate to complete current year
- 1.4 days
- Estimate to complete future years
- 0.0 days