May Report

Report Date
May 2014

Achievements in last period

  • Product Owners finalising their post implementation activities ready to commence use of new application
  • Updated code fix promoted to  to live on 12th May
  • Apps Management resource allocated to promote Business Objects activity test and live expected 9th and 16th June respectively

 

Issues

  • Apps Management have allocated resource for implementing business objects tasks however due to the ITS103 whereby both AIR and BI Suite databases are being migrated to new database infrastructure they have requested our activity takes place after test sign off of environments via ITS103 (now completed) and live deployment on 9th June.
  • There is a current risk impacting ITS103 whereby Student Systems have concerns regarding non availability of BI SUITE during ITS103 migration to live which may impact our activities. However PM is in discussions with other Project Manager to ensure our deployments remain on schedule.
  • Revised milestones have been approved via WIS for Bus Objects Deployment and Closure

 

Next Steps

  • Update Universe on Test
  • Promote Universe, Info space and Universe connection on live
  • Closure submit to WIS for approval

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
183.0 days
Activity this month
0.3 days
Activity this year
184.3 days
Activity to date
184.3 days
Estimate to complete current year
1.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Accident & Incident Reporting
Code
CSG002
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Karen Stirling
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
10-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Jun-2014