November 2015

Report Date
November 2015

Achievements in Last Period

  • Deployment dates secured for new instance, resources booked, deployment sign off and closure meetings booked for January 2016.
  • Extra budget secured

 

Issues

Scope change and milestone changes for creating the new SQL Instance has pushed this project into red.

 

Next Steps

  • Set up new SQL instance on shared server
  • Deploy to live on 11/12/15
  • Deployment Sign off Review in January 2016
  • Closure in January 2016

 

Milestones

11-Dec-2015Deploy new instance to LIVE
11-Jan-2016Deployment sign off review
19-Jan-2016Project closure
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
60.0 days
Activity this month
2.0 days
Activity this year
15.0 days
Activity to date
49.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
OPAS Migration
Code
CSG006
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Chris Konczak
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
19-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jan-2016
Category
Compliance

Documentation