November 2015
- Report Date
- November 2015
Achievements in Last Period
- Deployment dates secured for new instance, resources booked, deployment sign off and closure meetings booked for January 2016.
- Extra budget secured
Issues
Scope change and milestone changes for creating the new SQL Instance has pushed this project into red.
Next Steps
- Set up new SQL instance on shared server
- Deploy to live on 11/12/15
- Deployment Sign off Review in January 2016
- Closure in January 2016
Milestones
11-Dec-2015 | Deploy new instance to LIVE |
11-Jan-2016 | Deployment sign off review |
19-Jan-2016 | Project closure |
- Approved budget
- 60.0 days
- Activity this month
- 2.0 days
- Activity this year
- 15.0 days
- Activity to date
- 49.0 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days