Title Report Date Time Cost Scope Overall Change
Report for January 2017 January 2017 BLUE BLUE BLUE BLUE
Report for November 2016 November 2016 GREEN GREEN GREEN GREEN
Report for October 2016 October 2016 RED RED GREEN RED
Report for September 2016 September 2016 AMBER AMBER GREEN AMBER
Report for August 2016 August 2016 GREEN GREEN GREEN GREEN
Report for July 2016 July 2016 RED RED AMBER RED
Report for June 2016 June 2016 RED RED GREEN RED
Report for May 2016 May 2016 AMBER AMBER AMBER AMBER
Report for April 2016 April 2016 AMBER AMBER GREEN AMBER
Report for March 2016 March 2016 AMBER GREEN GREEN AMBER
Report for February 2016 February 2016 AMBER AMBER GREEN AMBER
Report for January 2016 January 2016 RED GREEN GREEN RED
Report for December 2015 December 2015 RED GREEN GREEN RED
Report for November 2015 November 2015 AMBER GREEN GREEN AMBER
Report for October 2015 October 2015 GREEN GREEN GREEN GREEN
Report for September 2015 September 2015 GREEN AMBER GREEN AMBER
Report for July 2015 July 2015 GREEN GREEN GREEN GREEN

Project Info

Project
Learning and Development Requirements for CSG
Code
CSG007
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Charles Hill
Current Stage
Close
Status
Closed
Start Date
01-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jan-2017
Category
Discretionary