Report for October 2016
- Report Date
- October 2016
Achievements in Last Period
- Reviewed project plans with Project Sponsor and representative Head of HR for CSG.
- Completed accessibility testing
- Commenced writing of contract
Issues
- The project budget has been exceeded, but the project sponosor has approved a 10 day budget increase to cover the additional feasibility and investigation work.
- The project delivery and closure dates have been missed but the project sponsor is aware of the work still required to complete the project
- As a result of the issues noted above, the project is showing as RED this month.
Next Steps
- Complete and sign contract
- Complete EqIA
- Arrange kick-off meetings for implementation project
- Undertake planning work for pilot
- Explore options and expected cost to integrate with MyEd Events Booking application
- Approved budget
- 48.0 days
- Activity this month
- 2.8 days
- Activity this year
- 9.6 days
- Activity to date
- 53.2 days
- Estimate to complete current year
- 4.2 days
- Estimate to complete future years
- 0.0 days