Report for November 2016

Report Date
November 2016

Achievements in Last Period

  • Discussed implementation plan
  • Reviewed contract
  • Requested purchase order
  • Agreed business units for pilot

Issues

  • None noted

Next Steps

  • Complete and sign contract
  • Complete EqIA
  • Arrange kick-off meetings with Business Leads
  • Close project in advance of new project request for implementation project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Learning and Development Requirements for CSG
Code
CSG007
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Charles Hill
Current Stage
Close
Status
Closed
Start Date
01-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jan-2017
Category
Discretionary

Documentation