This project will replace the current virtual servers that host the applications and databases used by Sport & Exercise to manage their membership, bookings, door access and reporting. The current servers have now been in place for five years, so it is thought that a replacement exercise would bring benefits to staff and users, as well as allow Sport & Exercise staff to make the most of upgraded versions of the software used as some of this (the reporting package, in particular) requires server upgrades.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2017 BLUE 23.0 days 24.5 days 0.0

Project Info

Project
Sport & Exercise Replacement Servers
Code
CSG010
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jim Aitken
Current Stage
Close
Status
Closed
Start Date
14-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.