Name Project Role Date Signed Off
Dave Berry Project Sponsor / Senior Supplier - Enterprise Architect (Project Team Member) 08-Jul-2019
Richard Bailey Project Manager (Project Team Member) 08-Jul-2019
Dawn Dodd Business Lead (50%) (Project Team Member) On annual leave - sign off covered by Catherine Hetherington
Catherine Hetherington Business Lead (50%) (Project Team Member) 08-Jul-2019
Brendan McGuckin Senior User (Project Team Member) 10-Jul-2019
Jason Murphy CRM Architect Lead / Consultant 08-Jul-2019
Sophie Milner Business Analyst (Project Team Member) 08-Jul-2019
Emma McNab Programme Manager 08-Jul-2019 (Verbal)
Alex Carter Head of Service Management, Project Stakeholder On paternity leave - sign off covered by Dave Berry
Alison Johnson Procurement Office Stakeholder 09-Jul-2019
Iain Fiddes Head of Development Services / Stakeholder On annual leave, Project Manager to check with Iain on his return
Mark Lang Development Technology Lead / Stakeholder 26-Jun-2019, Sign off against original Draft, Project Manager to check Mark is happy with updates on his return. 
Stefan Kaempf Head of Production Management, Licensing Stakeholder On Annual Leave - sign off covered by Suran Perera
Suran Perera Deputy Head of Production Management, Production Lead (Project Team Member) 09-Jul-2019

Date                   

Version      

Author                       

Section                     

Amendment                              

05/06/2019

Draft v0.1

Richard Bailey

All

Initial draft for review / discussion 

25/06/2019 Draft v0.2 Richard Bailey All Updates to the draft following workshops with key Stakeholders / Project Team Members during planning, including changes to scope and deliverables, as well as creating an estimate and milestones for review / agreement ahead of submission to WIS
02/07/2019 Draft v0.3 Richard Bailey All Final updates made, addressing feedback on deliverables, scope and budget to allow Brief to be circulated for sign off to allow it to be submitted to WIS
03-Jul-2019 Draft v0.4 Richard Bailey Objectives and Deliverables, Project Stakeholders / Document Sign Off List and Project Milestones

Deliverables, updates, D4 changed to “support processes” rather than “business processes” to clarify the scope of the project.  D13 "Agree the job description for the Service Manager post" has been added at the request of the Project Sponsor.  Project Stakeholder / sign off List have been updated to reflect that Sophie Milner is taking over as BA.  Milestones reflect budget secured into 2019/20 financial year

 

Project Info

Project
Industry Relationship Management (IRM) Service
Code
CSG016
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
29-Apr-2019
Planning Date
05-Jul-2019
Delivery Date
24-Jan-2020
Close Date
27-Mar-2020
Overall Priority
Higher
Category
Discretionary

Documentation

Plan