Industry Relationship Management (IRM) Service - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2020 BLUE 90.0 days 88.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 29 April 2019
Planning Date
Friday, 5 July 2019
Delivery Date
Friday, 24 January 2020
Close Date
Friday, 27 March 2020
Project information
Project Code
CSG016
Programme
CSG Portfolio Projects (OTHCSG)
Session
19/20
18/19
Organisational Unit
Corporate Services Group
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Funding Source
Core
Overall Priority
Higher
Student Impact
Project deliverables will have no impact on students
Specialist Skills
Communications
Marketing
Procurement