- Report Date
- March 2020
Achievements this Period
- Closure Report written.
- Additional detail on licences shared with the Head of Production.
- Project closure approved.
Issues
Next Steps
- Approved budget
- 90.0 days
- Activity this month
- 2.0 days
- Activity this year
- 88.0 days
- Activity to date
- 88.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days