Report for May 2019
- Report Date
- May 2019
Achievements this Period
- Project (New Project) initiated / agreed at WIS
- BA has started to engage tasks
Issues
- N/A
Next Steps
- Agree Stakeholders and Project Team
- Agree and set milestones
- Agree and secure resource bookings
- Define Project in ASTA
- Complete Project Brief / Planning / Estimate, including creating Project in ASTA
- Start to coordinate works
Milestones
TBC after Planning
Target Date![]() |
Title |
---|---|
14-Jun-2019 | |
19-Jul-2019 | Delivery |
02-Aug-2019 | Closure |
- Approved budget
- 25.0 days
- Activity this month
- 3.5 days
- Activity this year
- 5.6 days
- Activity to date
- 5.6 days
- Estimate to complete current year
- 20.9 days
- Estimate to complete future years
- 0.0 days