Report for June 2019
- Report Date
- June 2019
Achievements this Period
- Stakeholders and Project Team and have been agreed
- A draft Project Brief, planning and estimate have been completed and are with the Project Sponsor, Stakeholders and Project Team for approval
- Project created in ASTA
Issues
- N/A
Next Steps
- Confirm budget and Project timeline, splitting across financial years, with the Project Sponsor / Programme Manager
- Agree and secure resource bookings
- Confirm milestones
- Agree / sign off the Project Brief and submit to WIS
- Start to coordinate works
Milestones
TBC after Planning
Target Date![]() |
Title |
---|---|
05-Jul-2019 | |
23-Aug-2019 | Delivery |
30-Aug-2019 | Closure |
- Approved budget
- 25.0 days
- Activity this month
- 4.6 days
- Activity this year
- 10.3 days
- Activity to date
- 10.3 days
- Estimate to complete current year
- 10.1 days
- Estimate to complete future years
- 0.0 days