Report for June 2019

Report Date
June 2019

Achievements this Period

  • Stakeholders and Project Team and have been agreed
  • A draft Project Brief, planning and estimate have been completed and are with the Project Sponsor, Stakeholders and Project Team for approval
  • Project created in ASTA

 

Issues

  • N/A

 

Next Steps

  • Confirm budget and Project timeline, splitting across financial years, with the Project Sponsor / Programme Manager
  • Agree and secure resource bookings
  • Confirm milestones
  • Agree / sign off the Project Brief and submit to WIS
  • Start to coordinate works

 

Milestones

TBC after Planning

Target Datesort descending Title
05-Jul-2019           

End of Planning 

23-Aug-2019 Delivery
30-Aug-2019 Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
25.0 days
Activity this month
4.6 days
Activity this year
10.3 days
Activity to date
10.3 days
Estimate to complete current year
10.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Industry Relationship Management (IRM) Service
Code
CSG016
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
29-Apr-2019
Planning Date
05-Jul-2019
Delivery Date
24-Jan-2020
Close Date
27-Mar-2020
Overall Priority
Higher
Category
Discretionary

Documentation