Report for October 2019

Report Date
October 2019

Achievements this Period

  • Changes to the project plan and budget was supported by WIS.
  • Design requirements were further reviewed by team members and subsequently documented. 
  • Swift response to staff loss with alternative resource now recruited to fill the role of Business Analyst .

Issues

  • Unplanned loss of Business Analyst resource.
  • Limited availability of staff to schedule workshops with full attendance.

Next Steps

  • Project recovery re-plan with business to compensate for staff loss
  • Conclude the population of the Service Design Requirements
  • Complete the Data Privacy Impact assessment (DPIA)
  • Workshop in place with a subset of the project team to define a RACI matrix
  • Prepare a draft Service Design Package for team members to review.

Milestones

Milestone Due Date
End of Planning 12-Jul-2019
Map existing EI Business, Support and Training processes 04-Oct-2019
Determine support & reporting requirements / produce a Service Design Package 18-Oct-2019
Produce an Options Appraisal document 01-Nov-2019
Complete DPIA and Accessibility Review 01-Nov-2019
Delivery 08-Nov-2019
Produce a paper on CRM's technology utilised, what is to / not be consolidated and associated questions / decisions required    08-Nov-2019
Closure of Project 15-Nov-2019
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
It was with the loss of a Business Analyst with immediate affect that work over the last month has not been able to progress to plan and detrimentally impact expected milestones . This increases the risk to delivery of expected benefits which has dependencies to wider IRM development projects across UoE . Alternative resource has been recruited and is undergoing project familiarisation. The intention is to work closely with the business for an extended period over the next month and ideally produce a draft Service Design Document. From this, a project team review will be organised and a revised plan shaped for conclusion of any open actions.
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
Portfolio Manager has been advised.
Change Commentary
Some of the later milestones need to be re-planned, specifically associated with delivery and project closure.
Activity
Approved budget
74.0 days
Activity this month
6.0 days
Activity this year
25.8 days
Activity to date
46.4 days
Estimate to complete current year
24.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Industry Relationship Management (IRM) Service
Code
CSG016
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
29-Apr-2019
Planning Date
05-Jul-2019
Delivery Date
24-Jan-2020
Close Date
27-Mar-2020
Overall Priority
Higher
Category
Discretionary