Report for November 2019
- Report Date
- November 2019
Achievements this Period
- Project has returned to a RAG status of Green.
- Good progress has been made with documenting the RACI matrix.
- Service Design Requirements have been captured and these have been used to populate a Service Definition Document.
- On-going discussion has been had on procurement options appraisal.
Issues
- None.
Next Steps
- Complete the Data Privacy Impact Assessment (DPIA).
- Workshop arranged for a project wide review of project artefacts produced to date.
- Close present project with roles and responsibilities documented and with Service Management processes fully understood.
Note: the actual transition to a new Service Management arrangement will be progressed as a future project.
Milestones
Plan | End of Planning | 12-Jul-2019 |
Deliver | Delivery | 08-Nov-2019 |
Analyse | Map existing EI Business, Support and Training processes | 13-Nov-2019 |
Deliver | Determine support & reporting requirements / produce a Service Design Package | 29-Nov-2019 |
Deliver | Produce a Procurement Options Appraisal Document | 29-Nov-2019 |
Deliver | Project Artefacts Delivered | 09-Dec-2019 |
Deliver | Complete DPIA and Accessibility Review | 09-Dec-2019 |
Close | Project Closure | 20-Dec-2019 |
Close | DSOR Sign-off | 20-Dec-2019 |
- Approved budget
- 74.0 days
- Activity this month
- 13.0 days
- Activity this year
- 39.0 days
- Activity to date
- 59.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days