Overview

Background

As part of the consolidation of systems within Edinburgh Innovations and to reduce customer data held in silos, there is a requirement to deliver a Salesforce based Intellectual Property Management system that as a minimum provides all of the data and functionality currently utilised within Inteum, whilst maintaining secure access such that information and communications relating to Intellectual Property are only accessible by defined individuals with Edinburgh Innovations 

 

Scope

To migrate Inteum data and replicating Inteum functionalities and record security within Salesforce

To utilise the migration processes previously defined in CSG016 and update from lessons learned

To engage with the Digital Skills and Training Team in ISG to manage and support the delivery of IRM training 

Complete accessibility requirements through the completion of an EqIA

Update the current DPIA for the Salesforce IRM

 

Out of scope

Decommissioning of redundant infrastructure at Edinburgh Innovations

Resolving the licensing model for the IRM across the University 

Objectives

Priority – M = Must Have; S = Should Have; C = Could Have; W = Want 

  • M = has to be satisfied for the final solution to be acceptable in terms of delivery dates, compliance, viability etc. 

  • S = high-priority requirement that should be included if possible -workarounds may be available 

  • C = a nice-to-have requirement 

  • W = want but will not be part of this project 

  • O = Objective 

  • D = Deliverable 

Ref. Objectives and Deliverables Priority Owner
O1. Onboarding of IP team into Salesforce     
D1.1 Migration of Inteum data and replicating Inteum functionalities and record security within Salesforce M Business Lead 
D1.2 Determine Lessons learned from migration process S Business Lead 
O2. User Training Guides    
D2.1 Delivery of User Training Guide M EI Training Lead 
O3. System Related Documentation     
D3.1 Publication of Equalities Impact Assessment (EqIA) M Business Lead 
D3.2 Update existing DPIA to incorporate the IP team onboarding M Project Sponsor 
D3.3 Delivery of OLA M Project Manager 

 

Benefits

There are a number of benefits 

  • There is a potential reduction in overall costs  as the move towards a consolidated IRM service 
  • Enhanced functionality may also be a benefit as there are workflows and automations available in Salesforce that aren’t in Inteum
  • Project based approach for move to Salesforce
  • Alignment to UoE IRM / IT strategy
  • Change Management
  • Robust Training
  • Establishment of SLA’s/OLA’s

 

Success Criteria

The Onboarding of the IP team within Salesforce

Delivery of User Training Guides for future system users 

Determine lessons learned from the Onboardinng process 

Project Milestones

Stage Milestone Date
Planning  Planning 10/04/20
Execute

IRM Migration Preparation - Test

15/05/20
Execute 

IRM Migration Completed - Test

22/05/20
Execute

IRM Migration Review - Test

12/06/20
Execute

IRM Migration User Training

19/06/20
Execute

IRM Migration Sign Off - Test

19/06/20
Deliver

IRM Migration Go-Live

26/06/20
Deliver IRM Migration DSOR 10/07/20
Close Closure 17/07/20

 

Project Info

Project
IRM - Intellectual Property (IP) Team Onboarding
Code
CSG017
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Brendan McGuckin
Current Stage
Close
Status
Closed
Start Date
13-Mar-2020
Planning Date
27-Mar-2020
Delivery Date
14-Sep-2020
Close Date
17-Dec-2020
Overall Priority
Normal

Documentation

Plan