w/c 1st June 2020

  • IRM Configuration 
    • on-going 
  • Reports 
    • Draft overview of report with associated filters circulated 
  • Inventor Portal 
    • Outline design prepared 
    • Noted that
      • The Portal would now only be required to be used by the academics as the TT Team will undertake their admin tasks in SalesForce
      • The Portal is intended to be usable by Academics with no training or knowledge of the Technology Disclosure process
  • Project Plans 
    • currently being reviewed in light of delaying UT by one week
  • User Acceptance Testing 
    • UT held with PC (Technology)
    • Concerns raised regarding outstanding aspects of IRM configuration to be completed 
    • Concerns raised regarding the structure of the UAT testing - currently no TT process map available  - so fallback to use defined business requirements
    • UAT Issue Log created 
  • User Training 
    • Training content being developed 
    • TT IRM training examples being sought 

Project Info

Project
IRM - Intellectual Property (IP) Team Onboarding
Code
CSG017
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Brendan McGuckin
Current Stage
Close
Status
Closed
Start Date
13-Mar-2020
Planning Date
27-Mar-2020
Delivery Date
14-Sep-2020
Close Date
17-Dec-2020
Overall Priority
Normal