Report for June 2023
- Report Date
- June 2023
Achievements this period
- Produced test plan and test steps for UAT
- Commenced User Acceptance Testing
Issues
- The project sponsor has noted that it is likely they won't be able to complete user training prior to the next Audit and Risk Committee, and would like to consider delaying the deployment of the system until after that Committee meeting. The sponsor will discuss this within CSG factoring in the potential impact to budget, and confirm. As a result, the Time and Cost RAGs have been marked as AMBER this month.
Next Steps
- Decide on deployment timescale and, if required, revise milestones and secure budget to continue project into 23/24
- Complete User Acceptance Testing
- Prepare training materials