Title Report Date Time Cost Scope Overall Change
Report for May 2020 May 2020 GREEN

Project Info

Project
Openaire
Code
DCCOpenaire
Programme
Digital Curation Centre (DCC)
Management Office
ISG PMO
Project Manager
Kevin Ashley
Project Sponsor
Kevin Ashley
Current Stage
Close
Status
Closed
Start Date
08-Apr-2020
Planning Date
n/a
Delivery Date
n/a
Close Date
05-May-2021
Overall Priority
Normal