Report for April 2021

Report Date
April 2021

- Weekly catchups with ASLs, PM, ID and Learning Technologist (LT) are now underway.

- Linkages between LibSmart 1 & 2 content on both courses agreed and will be setup by the team.

- ID/LT to work with student intern on branding for promotion of LibSmart 2.

- Agreed with team that all screencasts can be recorded without the need for scripting as videos will be short and descriptive.

- Christine has confirmed that would like to use badges for LibSmart 2. LT & PM investigating how to implement this with wider team.

- Content is being applied to templates for ID/LT to review. ASLs are meeting with the teams supporting with content on regular basis.

- Some videos have been completed. However some will move into May due to busy workloads of ASLs.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LibSmart Phase II
Code
DLAS024
Programme
Distance Learning at Scale (DLAS)
Management Office
ISG PMO
Project Manager
Marcello Crolla
Project Sponsor
Jeremy Upton
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Nov-2020
Planning Date
05-Feb-2021
Delivery Date
01-Sep-2021
Close Date
29-Oct-2021
Overall Priority
Normal
Category
Discretionary

Documentation