Report for June 2021
- Report Date
- June 2021
Achievements in last period
-
Project brief and planning approved
-
Stakeholder Consultation sessions planned and underway
-
Organising Academics sessions
-
Business Analyst handover
Issues
-
Academic sessions to take place in July due to annual leave of project team members
Next Steps
-
Business Requirements gathering and documenting from stakeholder sessions
-
Agree Design and Infrastructure documentation outputs
The project status is GREEN
Milestones | Due Date |
---|---|
Phase 1 - Business Data Requirements – Current | 31-Jul-2021 |
Phase 1 - Business Data And Functional Requirements – Future | 31-Jul-2021 |
Phase 1 - Data Requirements & Design Complete | 31-Aug-2021 |
Phase 1 - Design for foundation infrastructure and baseline requirements complete | 31-Aug-2021 |
Phase 3 - API and Service Developments Commencement | 01-Sep-2021 |
Phase 2 - Software Installations and Infrastructure Builds Complete | 15-Oct-2021 |
Phase 4 - Service Rollout Commencement | 18-Oct-2021 |
Phase 3 - API and Service Developments Completion | 15-Oct-2022 |
Project Delivery complete | 30-Oct-2022 |
Phase 4 - Service Rollout Completion | 30-Oct-2022 |
Project Closure | 23-Dec-2022 |
- Approved budget
- 110.0 days
- Activity this month
- 8.3 days
- Activity this year
- 17.1 days
- Activity to date
- 17.1 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 80.0 days