Report for February 2021
- Report Date
- February 2021
Achievements in Last Period
- Formal Handover - not achieved - need support handover confirmed, possibly via Desktop CAB
Issues and Risks
Next Steps
- Formal Handover
Future Milestones
These dates are indicative until full planning is completed
Delivery | 30-Jun-2021 |
Closure | 30-Jul-2021 |
Project Sponsor Commentary / Approval
N/A
Attachment | Size |
---|---|
project_planning_-_guide_to_rag_status.docx | 31.66 KB |
- Approved budget
- 0.0 days
- Activity this month
- 1.5 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 20.0 days