Report for February 2022

Report Date
February 2022

Achievements in Last Period 

  • Workstream leads consulted to provide status reports
  • Discussions with James Saville in advance of James set to take over the lead/sponsor role for the programme
  • Exec paper updated with additional information

Issues 

  • Lack of clarity on communications requirements for the programme.  I am working with Shaun Burnett and Philip Graham to resolve this.

  • No hybrid working strategy has been communicated for the University, making it difficult to press ahead with the implementation.  An SLT meeting 30th March and Exec meeting 5th April will help with this.

Next Steps

  • First meeting of hybrid implementation group
  • Review workstream transition reports
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
338.0 days
Activity this month
6.3 days
Activity this year
111.4 days
Activity to date
257.6 days
Estimate to complete current year
80.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Hybrid Working Project
Code
DTFW01
Programme
Digital Transformation - Hybrid Working
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
Gavin McLachlan
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
09-Nov-2020
Planning Date
11-Jan-2021
Delivery Date
30-Apr-2022
Close Date
30-May-2022
Overall Priority
Higher
Category
Discretionary