ETL Implementation - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2019 AMBER 135.0 days 145.0 days 2.2
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 2 April 2018
Planning Date
Friday, 26 October 2018
Delivery Date
Friday, 17 May 2019
Close Date
Friday, 26 July 2019
Project information
Project Code
DTI005
Programme
Digital Transformation - Enterprise Data Warehouse
Session
18/19
17/18
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Programme Priority
1
Overall Priority
Higher