Report for May 2018
- Report Date
- May 2018
Achievements in Last Period
- Project transferred to new PM.
- TEST build complete, LIVE build in progress.
- Org/hierarchy application deployed to TEST with UAT completed and ASOR achieved.
- EDW Adapted BI/MI Service Organisation Document final draft complete.
- Completed sign-off of adapted BI/MI Service Document.
Issues
- Maintaining progress on infrastructure build through to project completion (expected date 08/06/2018).
Next Steps
- Achieve Deployment.
- Commence Project close activities.
The project showing as GREEN with focus continued on deployment and close of the project.
- Approved budget
- 360.0 days
- Activity this month
- 43.0 days
- Activity this year
- 322.7 days
- Activity to date
- 370.8 days
- Estimate to complete current year
- 12.9 days
- Estimate to complete future years
- 0.0 days