Report for June 2018
- Report Date
- June 2018
Achievements
- Infrastructure Build Complete Milestone achieved – We now have a ‘Production Ready’ Enterprise Data Warehouse;
- Deployment Checklist completed;
- Go CAB approved deployment to LIVE environment for Production;
- Parameritisation completed and pushed out to environments
Issues
- Security Patch applied to DEV which locked the container to all users. DEV had to be rolled back which caused a delay to EST109 development. Security patch has been applied to TEST and LIVE and will be applied to DEV once EST109 demonstrations have been completed;
- Some items within DTI006 have been descoped and will be carried across to DTI021 (EDW Embed and Optimise) for completion
Next Steps
- EDW Implementation to completed before EDW is deployed on the 16th July;
- TAD to be signed off by CISO;
- DSOR to be completed;
- Parameritisation documentation to be completed.
- Approved budget
- 397.0 days
- Activity this month
- 18.8 days
- Activity this year
- 344.1 days
- Activity to date
- 392.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days