Report for July 2018
- Report Date
- July 2018
Achievements
- All remaining DTI006 JIRAs reviewed and closed with no further action.
- EDW deployed on 16th July 2018.
- DSOR completed and signed off on 3rd August 2018.
- Project closed on 3rd August 2018.
Issues
- Final project came in 8.5 days over the agreed budget (405.5 days versus 397 budgeted days).
Next Steps
- Some items within DTI006 have been de-scoped and will be carried across to DTI021 (EDW Embed and Optimise) for completion.
- Security patch will be applied to DEV once EST109 demonstrations have been completed.
- Approved budget
- 397.0 days
- Activity this month
- 12.4 days
- Activity this year
- 358.4 days
- Activity to date
- 405.5 days
- Estimate to complete current year
- 0.4 days
- Estimate to complete future years
- 0.0 days