Project Brief
Link to Project Brief and End of Planning Sign Off
Version Control
Date |
Change agreed |
Version |
Change |
Made by |
5/4 |
EdGEL Steering Group |
1.1 |
O2D1 Insights report – moved to O1D1 as an appendix |
SW |
O1D3 Website review – Billy cant pick up to nearer end June – dates changed from 22/5-2/6 to 19-30Jun |
||||
O1D4 Style guide dates agreed as 6 Mar – 31 May (from 28 Apr)
|
||||
O2D2 adoption strategy backlog document - moved out to end May so Karl can concentrate on other tasks |
||||
O3D2- Gap Analysis – Mairi’s time not required – removed from this task
|
||||
Date changes have affected milestones – changes are Recommendations to continue EdGEL was 28-Apr-17 now 30-Jun-17 Framework for delivering EdGEL was 23-Jun-17 now 30-Jun-17
|
||||
12/5 |
Project Sponsor |
1.1 |
EdGEL Style Guide V1.0 (O1 D4) - It is now a 'Review of the existing style guide' - See piccl 5 |
SW |
17/5 |
Project Sponsor |
1.1 |
O3D1 Dropped ‘Initial’ from deliverable title and Benefit– see piccl 6 17/5 |
SW |