Report for April 17

Report Date
April 2017

Achievements in Last Period

  • An EdGEL Steering Group meeting of 5 April confirmed deliverables and timelines for all 4 projects (piccl 3 lists the milestone changes for DTI007)
  • The deliverable for Gap Analysis was approved 24 April
  • The deliverable for the Hackathon plan was approved 24 April

Issues

  • The Style Guide (O1 D4) deliverable was 30 May (agreed at EdGEL Steering Group of 5 April). However this will be a large piece of work and cannot be delivered by 30 May due to the other work the consultant has to deliver in this timeframe so to give time to implement this piece of work properly the sponsor asked for 7th July to be the deliverable date. This deliverable is aligned to the milestone ‘Framework for delivering EdGEL’ with a due date of 30 June so the milestone date was also moved to 7 July to accommodate the Style Guide deliverable

Next Steps

  • EdGEL Website Update review and proposal completed by 19 May. Consultant informs that this likely to finish well before the deadline
  • Next milestones will be the end of May

Project is GREEN

Milestones

30-Jun-2017

 Recommendations to continue EdGEL

07-Jul-2017

 Framework for delivering EdGEL

07-Jul-2017

 Engagement strategy initiation

17-Jul-2017

Delivery

26-Jul-2017

Close

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
47.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdGEL as a Service
Code
DTI007
Programme
Digital Transformation - User Experience
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
20-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jul-2017
Overall Priority
Higher
Category
Discretionary