Organisation
Work/Task Breakdown
Planning (DTI018 Project) |
Produce Project Brief |
Agree estimates |
Planning Review / Sign-off Project Brief |
Design |
Deliver reduced deployment checklist template |
Deliver reduced system description document template |
Deliver reduced TAD template |
Deliver blueprints for Java and Python |
Build |
Build activities |
Integrate |
Integration activities |
Accept |
Acceptance activities |
Delivery |
Deploy to Live |
Handover to Production Management and Service Management |
Deployment Support |
Delivery |
Closure (DTI018 Project) |
Deployment Review |
Closure Report |
Close |
Resources, Skills and Costs
Resources from the following teams are required to deliver this project:
- Project Services
- Development Technology
- Software Development
- Enterprise Architecture
- Service Management
- Applications Management
- Technology Management
The project is funded from the Digital Transformation Portfolio and has 23 days allocated within 2016/17 (see PRICCL Change 4 for summary).
Project Governance
Project Sponsor will provide direction.
Project Manager will manage the project on a day to day basis.
The Programme Steering Group terms of reference is below.
enterprise_apis_steering_group_tor_0.3.pdf