Report for May 17

Report Date
May 2017

Achievements in Last Period

  • Project kicked off following PM leave at start of May
  • Invite to Quote created to recruit a  BI/MI Analyst.

 

Issues

  • No issues so far

 

Next Steps

  • Project Brief sign off - project brief will be out for review week beginning 5 June
  • Recruitment of consultant BI/MI Analyst

Milestones

06-Jun-2017 End of Planning
08-Aug-2017 Delivery
18-Aug-2017 Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
1.9 days
Activity this year
2.8 days
Activity to date
2.8 days
Estimate to complete current year
39.0 days
Estimate to complete future years
8.0 days

Project Info

Project
BI/MI Analysis Toolkit
Code
DTI019
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Andrew McFarlane
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2017
Planning Date
26-Jun-2018
Delivery Date
25-Jul-2018
Close Date
31-Aug-2018
Overall Priority
Normal
Category
Discretionary