Report for March 18
- Report Date
- March 2018
Achievements
-
- Revised milestones approved by WIS 26 January 18
- PM drew up a revised toolkit document but on consultation with other analysts working on BI there needs to be changes
Issues
- PM had to take on 2 new projects and had deadlines for the project briefs which meant the toolkit update was delayed
- Snowstorm and closure of university delayed the review of the revised toolkit
Next Steps
- Update of revised toolkit
- PM to reconsider milestones as redrafting delayed
Milestones
16-Feb-2018 | Redrafting of toolkit as UoE toolkit (new) |
09-Mar-2018 | Approval by Operational Guidance Committee |
13-Mar-2018 | Delivery of BI/MI Analysis Toolkit into overarching BI/MI Projects toolkit |
20-Mar-2018 | Delivery Review |
23-Mar-2018 | Close |
Project is amber as milestones are to be reviewed
- Approved budget
- 45.0 days
- Activity this month
- 1.0 day
- Activity this year
- 30.3 days
- Activity to date
- 39.0 days
- Estimate to complete current year
- 6.4 days
- Estimate to complete future years
- 0.0 days