Report for June17

Report Date
June 2017

Achievements in Last Period

  • Project Brief completed 26 June
  • Invitations to quote for BI/MI Analysis sent out and interviews are under way

 

Issues

  • Project Brief rejected at WIS as no signoff from EDW governance and PM still chasing

 

Next Steps

  • BI/MI Analyst to start work on toolkit

Milestones

04-Aug-2017

BI/MI Analysis Toolkit created and reviewed

15-Aug-2017

Delivery of BI/MI Analysis Toolkit into overarching BI/MI Projects toolkit

22-Aug-2017

Delivery Review

29-Aug-2017

Close

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
61.0 days
Activity this month
4.9 days
Activity this year
7.7 days
Activity to date
7.0 days
Estimate to complete current year
46.0 days
Estimate to complete future years
8.0 days

Project Info

Project
BI/MI Analysis Toolkit
Code
DTI019
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Andrew McFarlane
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2017
Planning Date
26-Jun-2018
Delivery Date
25-Jul-2018
Close Date
31-Aug-2018
Overall Priority
Normal
Category
Discretionary