Report for July 17

Report Date
July 2017

Achievements in Last Period

  • Project Brief approved at WIS
  • ITQ created and sent out to selected firms for BI/MI Analyst consultancy post
  • Interviews held
  • Recruitment and SOW agreed 

 

Issues

  • Nil issues this month

 

Next Steps

  • BI/MI Analyst to start work on 14 August

Milestones

13-Oct-2017

  BI/MI Analysis Toolkit created and reviewed

24-Oct-2017

  Delivery of BI/MI Analysis Toolkit into overarching BI/MI Projects toolkit

31-Oct-2017

  Delivery Review

8-Nov-2017

  Close

 

Note: these revised milestones are being submitted to WIS this week

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
61.0 days
Activity this month
0.5 days
Activity this year
8.2 days
Activity to date
8.2 days
Estimate to complete current year
3.5 days
Estimate to complete future years
49.5 days

Project Info

Project
BI/MI Analysis Toolkit
Code
DTI019
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Andrew McFarlane
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2017
Planning Date
26-Jun-2018
Delivery Date
25-Jul-2018
Close Date
31-Aug-2018
Overall Priority
Normal
Category
Discretionary