The embed & optimise project follows on from project DTI006 (EDW Implementation) with the aim of evolving EDW from a 'production ready' service with a limited  amount of early adoption usage an 'enterprise ready' one, capable of supporting full scale business acquisition projects and BAU activity.    

Part of Digital transformation.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2019 139.0 days 141.0 days 0.0

Project Info

Project
EDW - Embed & Optimise
Code
DTI021
Programme
Digital Transformation - Enterprise Data Warehouse
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
21-May-2018
Planning Date
17-Aug-2018
Delivery Date
30-Apr-2019
Close Date
02-May-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Project Dashboard

Change dashboard

Nothing to report.