Define Document Management Service - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2018 BLUE 275.0 days 279.9 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 27 November 2017
Planning Date
Friday, 30 March 2018
Delivery Date
Friday, 7 September 2018
Close Date
Friday, 28 September 2018
Project information
Project Code
DTI030
Programme
Digital Transformation - Document Management (DTIP07)
Session
18/19
17/18
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Funding Source
Funded by DTI
Overall Priority
Normal