Report for August 2018

Report Date
August 2018

Define Document Management Service 

Barry Ure

Achievements in Last Period

  • PICCL approved for new milestone - Signing off of the Report by the project board ( 7/09/2018)

Next Steps

  • Get Report Signed off by project Board 
  • Close project and agree next steps 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Replanning and use of extra resources to mitigate
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
275.0 days
Activity this month
27.0 days
Activity this year
153.0 days
Activity to date
153.0 days
Estimate to complete current year
106.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Define Document Management Service
Code
DTI030
Programme
Digital Transformation - Document Management (DTIP07)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Catherine Hetherington
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
27-Nov-2017
Planning Date
30-Mar-2018
Delivery Date
07-Sep-2018
Close Date
28-Sep-2018
Overall Priority
Normal
Category
Discretionary

Documentation