Report for September 2018

Report Date
September 2018

Define Document Management Service 

 

Achievements in Last Period

  • Project report approved by the project board
  • Project closure report approved
  • Project closed at WIS on 28/09/18

Issues

  • None

Next Steps

  • None
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
275.0 days
Activity this month
5.6 days
Activity this year
16.9 days
Activity to date
279.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Define Document Management Service
Code
DTI030
Programme
Digital Transformation - Document Management (DTIP07)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Catherine Hetherington
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
27-Nov-2017
Planning Date
30-Mar-2018
Delivery Date
07-Sep-2018
Close Date
28-Sep-2018
Overall Priority
Normal
Category
Discretionary

Documentation