Report For February 2018

Report Date
February 2018

Achievements this period

An requirements gathering exercise has been carried out and the requirements for the existing proposal to procure Qlikview have been established

Issues

Additional opportunities have been offered by Qlikview. These are currently being reviewed. It they prove worthwhile then this will have significant impact on the project

 

Next Steps

Review the new opportunity with the Project Sponsor and Owner.

Review the project plan and obtain appropriate sign off.

Check that the procurement route remains valid

Sign off the requirements and submit to the vendor

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Additional opertunities have been offered by Qlikview. These are currently being reviewed. It they prove worthwile then this will have significant impact on the project
Change Status
Activity
Approved budget
40.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
QlikView Consolidation (DTI033)
Code
DTI033
Programme
Digital Transformation - BI Tools (DTIP08) - CLOSED
Management Office
ISG PMO
Project Manager
Jay Heer
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
21-Dec-2017
Planning Date
26-Jan-2018
Delivery Date
27-Jul-2018
Close Date
27-Aug-2018
Overall Priority
Normal
Category
Discretionary

Documentation