Report For March 2018

Report Date
March 2018

Achievements this period

A highly advantageous package is in the final stages of negotiation with vendors which delivers all the basic requirements ad a lot  more

Issues

This has taken longer than anticipated

 

Next Steps

Complete the procurement

Close the project

 

 

 

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Additional opertunities have been offered by Qlikview. These are currently being reviewed. It they prove worthwile then this will have significant impact on the project
Change Status
Activity
Approved budget
40.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
QlikView Consolidation (DTI033)
Code
DTI033
Programme
Digital Transformation - BI Tools (DTIP08) - CLOSED
Management Office
ISG PMO
Project Manager
Jay Heer
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
21-Dec-2017
Planning Date
26-Jan-2018
Delivery Date
27-Jul-2018
Close Date
27-Aug-2018
Overall Priority
Normal
Category
Discretionary

Documentation