Report for July 2018

Report Date
July 2018

Achievements this period

  • Qlikview / Qliksense contract awarded and PO issued.  

Issues

  • Project Manager left UofE. Programme manager has taken over PM duties.

Next Steps

  • Close Project

The project is reporting a status of AMBER, due to the late closure.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Late close of project, due to PM leaving UofE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
5.0 days
Activity this year
60.0 days
Activity to date
60.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
2.0 days

Project Info

Project
QlikView Consolidation (DTI033)
Code
DTI033
Programme
Digital Transformation - BI Tools (DTIP08) - CLOSED
Management Office
ISG PMO
Project Manager
Jay Heer
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
21-Dec-2017
Planning Date
26-Jan-2018
Delivery Date
27-Jul-2018
Close Date
27-Aug-2018
Overall Priority
Normal
Category
Discretionary

Documentation