Delivery Milestone Report for 24/11/20
- Report Date
- November 2020
Delivery Milestone Report for 24th November 2020
Project Status
RAG Status - Green
Overview
Delivery of a virtual tour solution for SRA that provides, through an interactive map containing information hotspots and rich media assets, a space and place representation of the University and its environs. This will be a key tool at a time when physical visits are not possible and likely to be constrained for some time.
Next Delivery Milestone: UoE Sign Off Service Wrapper - Now proposed as 25-Nov-2020 (was 11-Nov-2020)
RAG Commentary
- The site was officially launched / is live 02-Nov-2020.
- Work is still underway to apply a Service Wrapper, the BA is in discussion with SRA, Enquiry Management and IS to finalise.
- Works underway agreeing publication and site content creation BAU processes. This has now been agreed to extend beyond the main Project life cycle.
- A draft closure report has been created and was reviewed 16-Nov-2020.
- Project Closure is now predicted for 27-Nov-2020. It was agreed that to complete the Service Wrapper that the PM raise a Change #4: Change to Major Milestone - Project Closure in support of this, which will be submitted to WIS 20-Nov-2020.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days