Delivery Milestone Report for 24/11/20

Report Date
November 2020

Delivery Milestone Report for 24th November 2020

Project Status

RAG Status  - Green

Overview

Delivery of a virtual tour solution for SRA that provides, through an interactive map containing information hotspots and rich media assets, a space and place representation of the University and its environs. This will be a key tool at a time when physical visits are not possible and likely to be constrained for some time.

Next Delivery Milestone:  UoE Sign Off Service Wrapper - Now proposed as 25-Nov-2020 (was 11-Nov-2020)

 

RAG Commentary

  • The site was officially launched / is live 02-Nov-2020.
  • Work is still underway to apply a Service Wrapper, the BA is in discussion with SRA, Enquiry Management and IS to finalise.
  • Works underway agreeing publication and site content creation BAU processes.  This has now been agreed to extend beyond the main Project life cycle.
  • A draft closure report has been created and was reviewed 16-Nov-2020. 
  • Project Closure is now predicted for 27-Nov-2020.  It was agreed that to complete the Service Wrapper that the PM raise a Change #4:  Change to Major Milestone - Project Closure in support of this, which will be submitted to WIS 20-Nov-2020.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
The site was launched / went live on Monday 2nd November 2020. Works are underway to create / agree a Service Wrapper and agree BAU processes for content creation / amends. Closure activities have started. Expected project closure is now 27-Nov-2020.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
The site was launched / went live on Monday 2nd November 2020. Works are underway to create / agree a Service Wrapper and agree BAU processes for content creation / amends. Closure activities have started. Expected project closure is now 27-Nov-2020.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Virtual Visits
Code
DTI056
Programme
Digital Transformation - Online and Digital Events Programme (DTIODE)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Clare Mackay
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
09-Jul-2020
Planning Date
18-Sep-2020
Delivery Date
26-Oct-2020
Close Date
04-Dec-2020
Overall Priority
Highest
Category
Discretionary

Documentation