Report for December 2020
- Report Date
- December 2020
Key Achievements in the Last Period
- The site was officially launched / is live 02-Nov-2020.
- An IS News Story has been published in support of launch.
- Work is still underway to apply a Service Wrapper, the BA is in discussion with SRA, Enquiry Management and IS to finalise. It is likely that a number of items will remain to be completed post Project as part of the formation of the wider Online and Digital Events Service, which includes EventsAir and Unibuddy.
- Agreement has been reached with Service Excellence that works will continue post Project to agree / finalise publication and site content creation BAU processes.
- A draft closure report was created, reviewed (16-Nov-2020) and approved, it was submitted to WIS (04-Dec-2020).
- Project Closure was agreed 04-Dec-2020.
Next Phase Tasks
- None
Issues and Risks
- None
Milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Plan | Complete Project Planning | 18-Sep-2020 | No date available | Yes | |
Execute | UoE Supply Background Map to RV | 05-Oct-2020 | No date available | Yes | |
Execute | RV Release V2 Application to UoE for Review | 07-Oct-2020 | No date available | Yes | |
Execute | UoE Supply Feedback on Application V2 to RV | 09-Oct-2020 | No date available | Yes | |
Execute | RV Update / Respond to Security Questions | 09-Oct-2020 | No date available | Yes | |
Execute | UoE Supply Final Zoomed in Detailed Map to RV | 12-Oct-2020 | No date available | Yes | |
Accept | UoE Content Review (Schools) Starts (Against basic / zoomed out map) | 12-Oct-2020 | No date available | Yes | |
Execute | RV Release Final Application V3 for Review | 15-Oct-2020 | No date available | Yes | |
Accept | UoE Supply Final Feedback on V3 to RV | 16-Oct-2020 | No date available | Yes | |
Execute | UoE Load Final Launch Content for Review / Sign Off | 16-Oct-2020 | No date available | Yes | |
Accept | UoE Sign off Site Functionality to RV | 19-Oct-2020 | No date available | Yes | |
Deliver | RV Move Code from Staging to LIVE | 20-Oct-2020 | No date available | Yes | |
Accept | Achieve Accessibility and CISO Sign Off | 23-Oct-2020 | 16-Oct-2020 | Yes | |
Accept | Website Content Reviewed / Signed Off Ready for Launch | 23-Oct-2020 | No date available | Yes | |
Deliver | Website Go Live | 26-Oct-2020 | No date available | Yes | |
Accept | UoE Sign Off Service Wrapper | 25-Nov-2020 | 11-Nov-2020 | Yes | |
Close | Project Closure | 27-Nov-2020 | 13-Nov-2020 | Yes |
- Approved budget
- 50.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 39.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days