January Update

A programme planning day was scheduled for the 18th, which set out dates for DTP001 and the other projects, many of which interact with each other.

 

It is clear now that the team doe snot have the expertise to move the project onto the next stage of analysis and design - Graham is recourcing a specifialist consutlant

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance