Second set of workshops completed - ready for Design

 

 

February has seen two sets of workshops, with Softcat meeting key folk from all the UOE stakeholders - colleges, ITI, Apps, LTW and USD.

Softcat have most of the information needed to now move onto design and refine the plan, so we can book the UoE resources needed

Plenty of follow up actions but project progressing well

 

Project Board meet on 11th April

 

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance