August 2016

Report Date
August 2016

Overview

Achievements in Last Period

  • completion of requirements gathering and prioritisatin from colleges and groups
  •  

Issues and Risks

  • no amber or red risks

Next Steps

  • complete ITT
  • issue tender

 

Project status set to Amber as ITT pushed back a fortnight

 

 

Future Milestones

 

19-Sep-2016ITT Published
11-Nov-2016Award Contract
31-Mar-2017Complete Deployment of Apps to User Devices
31-Mar-2017Security Acceptance Sign-off
21-Apr-2017Closure of Project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance