October 2016

Report Date
October 2016

Overview

Achievements in Last Period

  • issue ITT - achieved

Issues and Risks

  • no amber or red risks

Next Steps

  • receive and assess tender responses
  • presentations
  • final scores and award contact

 

Future Milestones

07-Oct-2016 ITT Published
31-Oct-2016 Sign-off Service Deployment
07-Nov-2016 Tender Return
25-Nov-2016 Award Contract
28-Apr-2017 Start Pilot Service
28-Jul-2017 Complete Deployment of Apps to User Devices
28-Jul-2017 Security Acceptance Sign-off
10-Nov-2017 Closure of Project

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
59.0 days
Activity this month
2.0 days
Activity this year
18.5 days
Estimate to complete current year
40.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance